2024.2 Project Priorities

The Dalmatian Cycle priorities were discussed during Dalmatian Virtual PTG. The preliminary list was maintained on the Dalmatian PTG etherpad.

The following indicates milestonewise priorities.

Priority Item

Owner(s)

Spec(s)

Target release milestone

Deprecate metadata_encryption_key

Pranali Deore

deprecate metadata encryption key

M1

New Location APIs

Pranali Deore

new location apis

M2

New sub-store NFS for FS store

Abhishek Kekane

improve_filesystem_driver

M2

Add CLI utility for migrating images

Abhishek Kekane

None

M3

Removed all unused config options

Cyril Roelandt

None

M3

All image/metadef APIs OSC & SDK Support

Mridula Joshi

None

M3

Image Encryption

Josephine Seifert

image encryption

M3

Important dates

This is an abbreviated list focused on dates relevant to Glance. See Dalmatian Release Schedule for the complete list for OpenStack.

Milestone

Week of

What

R-20

May 17

Dalmatian-1 Milestone

R-13

Jul 05

  • Dalmatian-2 Milestone

  • Glance Spec freeze

R-6

Aug 23

glance_store Dalmatian release (final release for non-client libraries)

R-5

Aug 30

  • Dalmatian-3 milestone

  • Glance feature freeze

  • python-glanceclient dalmatian release (final release for client libraries);

R-3

Sept 13

RC-1 release and string freeze

R-1

Sept 27

final RCs

R-0

Oct 04

Dalmatian release