2024.2 Project Priorities¶
The Dalmatian Cycle priorities were discussed during Dalmatian Virtual PTG. The preliminary list was maintained on the Dalmatian PTG etherpad.
The following indicates milestonewise priorities.
Priority Item |
Owner(s) |
Spec(s) |
Target release milestone |
---|---|---|---|
Deprecate metadata_encryption_key |
M1 |
||
New Location APIs |
M2 |
||
New sub-store NFS for FS store |
M2 |
||
Add CLI utility for migrating images |
None |
M3 |
|
Removed all unused config options |
None |
M3 |
|
All image/metadef APIs OSC & SDK Support |
None |
M3 |
|
Image Encryption |
M3 |
Important dates¶
This is an abbreviated list focused on dates relevant to Glance. See Dalmatian Release Schedule for the complete list for OpenStack.
Milestone |
Week of |
What |
---|---|---|
R-20 |
May 17 |
Dalmatian-1 Milestone |
R-13 |
Jul 05 |
|
R-6 |
Aug 23 |
glance_store Dalmatian release (final release for non-client libraries) |
R-5 |
Aug 30 |
|
R-3 |
Sept 13 |
RC-1 release and string freeze |
R-1 |
Sept 27 |
final RCs |
R-0 |
Oct 04 |
Dalmatian release |