2024.1 Project Priorities¶
The Caracal Cycle priorities were discussed during Caracal Virtual PTG. The preliminary list was maintained on the Caracal PTG etherpad.
This list is an estimate of what the Glance project team can accomplish during the 2024.1 Cycle based on our developer’s estimates of how much time they can commit to Glance.
The following indicates milestonewise priorities.
Priority Item |
Owner(s) |
Spec(s) |
Target release milestone |
---|---|---|---|
New Location APIs |
M2 |
||
Centralize DB for cache |
M2 |
||
Deprecate Location Strategy |
M2 |
||
Deprecate Cachemanage middleware |
M2 |
||
Remove/Migrate Single Store Tests |
None |
M3 |
|
All image/metadef APIs OSC & SDK Support |
None |
M3 |
|
Image Encryption |
M3 |
Important dates¶
This is an abbreviated list focused on dates relevant to Glance. See Caracal Release Schedule for the complete list for OpenStack.
Milestone |
Week of |
What |
---|---|---|
R-20 |
Nov 17 |
Caracal-1 Milestone |
R-12 |
Jan 12 |
|
R-6 |
Feb 23 |
glance_store Caracal release (final release for non-client libraries) |
R-5 |
Mar 01 |
|
R-3 |
Mar 15 |
RC-1 release and string freeze |
R-1 |
Mar 29 |
final RCs |
R-0 |
Apr 05 |
Caracal release |